LATEST
NEWS

Richard Humphreys
/ Categories: News

Loch Lomond nears completion of huge drainage project

Loch Lomond Golf Club in Scotland is nearing completion of a four-year renovation project to transform the course’s drainage. 

Costing £7.5 million, the project has seen a complete rebuild of the drainage infrastructure including extensive sandcapping. The irrigation system has also been renewed and bunkers have been reconstructed with the Capillary Bunkers lining system.  

“We have a lot of bunkers – and a lot of rain,” said David Cole, the club’s director of golf course and estates. “We average around 2,000 millimetres of rain a year, and our bunker design has some steep faces in places. As a result, we have always suffered badly from washouts and contamination. 

“Bunker maintenance is our second largest consumer of greenkeeping resources, second to greens – due to the design, the size, the amount, the player expectations and the environment, it takes a lot of resources to prepare the bunkers internally and externally for play on a daily basis, and it was frustrating not being able to produce a consistently good product from this valuable resource due to the ageing infrastructure and the uncontrollable element of frequent rainfall.” 

Work has included lining the drainage trenches with geotextile to prevent the ingress of particles into the pipes, which have also been resized to cope better with the volume of water. 

Cole and his team have worked alongside contractor GolfLink Evolve since starting the project in winter 2017/18 when holes 14 and 15 were rebuilt as a trial. The project was planned to be completed over the winter of 2019/20, but the Covid-19 pandemic meant that two holes were left unfinished. Those have been completed over winter 2020/21. 

Read more about the project in our report from the January 2020 issue of Golf Course Architecture

Cole also wanted to improve the consistency of bunker presentation. “We wanted to eliminate sand contamination and washouts and ensure we give our members a quality product no matter the weather,” he said. “After reviewing and trialling the options available, we selected Capillary Concrete throughout the project to line the bunkers. 

“The fact that you can install in wet weather situations is a huge plus for us as the renovation and installations took place throughout the wettest period of the year.” 

Cole says he is already seeing the benefits. “We aren’t spending hours pushing sand back up bunker faces after rain. Since the liner has been installed, the sand does not slip off the face after heavy rain events and daily preparations to present a good product for our members and guests is less labour intensive than previous. This allows us to focus more time on the detail work of internal bunker maintenance, and/or redirect resources to other priority areas that been neglected prior to this undertaking. I think we may see a 40-50 per cent reduction in resources we use preparing the internals of bunkers, yet still producing a superior product.” 

 

Previous Article Cherokee CC in Wisconsin appoints team to develop renovation plan
Next Article Spring 2021 issue of ASGCA’s By Design magazine is out now
Print
4549 Rate this article:
No rating
Slideshow HTML
  • Loch Lomond
    Loch Lomond GC

    Loch Lomond Golf Club in Scotland is nearing completion of a four-year renovation project

  • Loch Lomond
    Loch Lomond GC

    The course has been sandcapped and bunkers have been lined with the Capillary Bunkers system

ADd Image Credit here for home page
Loch Lomond GC
Richard Humphreys

Richard HumphreysRichard Humphreys

Other posts by Richard Humphreys
Contact author

Contact author

x
Winter 2024 issue of ASGCA’s By Design magazine is out now
Magazine, News | Wed 11 Dec, 2024

Winter 2024 issue of ASGCA’s By Design magazine is out now

Golf course architects take on the challenge of redesigning the Road hole at St Andrews

The October 2024 issue of Golf Course Architecture is out now!
Magazine, News | Thu 17 Oct, 2024

The October 2024 issue of Golf Course Architecture is out now!

The Keep at McLemore, a Bill Bergin-Rees Jones mountaintop design in northwest Georgia, features on the cover

FEATURE
ARTICLES

Taking time to recapture character
Inwood Country Club
Opinion | Daniel Friedman

Taking time to recapture character

Inwood’s Daniel Friedman talks about how the New York club has spent the last 20 years trying to make up for the previous 80 years of change that had slowly eroded the character of its Herbert Strong-designed course

A masterpiece comes into view
Cobbs Creek
Opinion | Mark Wagner

A masterpiece comes into view

Mark Wagner provides an update on progress of the revival of Cobbs Creek

Bill Amick: Long calling for short
ASGCA
Interview | Adam Lawrence

Bill Amick: Long calling for short

Adam Lawrence spoke to the designer about his life and his attempts to encourage golfers to play shorter courses

The triumph of the Dyeciples
ASGCA
Feature | Adam Lawrence

The triumph of the Dyeciples

Adam Lawrence asks why architects who trained with Pete Dye are so dominant in today’s golf design business

The Keep: On top of the world
Evan Schiller
On site | Richard Humphreys

The Keep: On top of the world

Richard Humphreys reports on a new layout that is destined to catch the eye. Designed by Bill Bergin and Rees Jones, McLemore’s second course occupies a spectacular setting on a mountaintop plateau

Goodwood: Down in the woods
Report | Richard Humphreys

Goodwood: Down in the woods

Golf At Goodwood has a new practice facility designed by James Edwards and built by MJ Abbott

Cedar Rapids: Blown away
Vaughn Halyard
On site | Adam Lawrence

Cedar Rapids: Blown away

After an acclaimed 2015 restoration by Ron Prichard, Iowa club thought it was set fair for the future. But Mother Nature had other ideas, says Adam Lawrence

North Ranch: Time for transformation
North Ranch CC
Report | Richard Humphreys

North Ranch: Time for transformation

Fifty years after it was originally laid out, the Ted Robinson layout has been re-envisioned by Jackson-Kahn Design and rebuilt by Landscapes Unlimited

Team building
Turfgrass
Interview | Richard Humphreys

Team building

Turfgrass has launched its US arm with the appointment of John Lawrence, Adam Moeller and Brad Owen. Richard Humphreys speaks with them, Turfgrass founder John Clarkin and director of agronomy Julian Mooney to find out more

Birdie Act: An end to templates?
Kevin Murray
Feature | Adam Lawrence

Birdie Act: An end to templates?

Legislation before the US Congress would extend the copyright protection that currently exists for buildings architecture to golf course design. But would that preclude the construction of classic hole designs, asks Adam Lawrence?

The art of project management
Leeds Golf Design
Opinion | Giulia Ferroni

The art of project management

Giulia Ferroni of Leeds Golf Design spells out the intricacies of executing a masterplan and the skills required from a golf course architect

Gopher Watch Competition – October 2024
Gopher Watch, News | Mon 21 Oct, 2024

Gopher Watch Competition – October 2024

Which course has Sandy the gopher visited this month?

MOST
POPULAR

FEATURED
BUSINESSES